摘要
结合丹东至通化高速公路工程对40m预应力混凝土T梁施工、安全、环保的特殊要求,介绍了40m混凝土T梁的主要制作工艺。
Combining with special requirements to construction, safety and environmental protection of 40m prestressed concrete T - girder in Dandong - Tonghua expressway engineering, the main pre - casting process of 40m concrete T- girder is introduced.
出处
《北方交通》
2010年第8期36-38,共3页
Northern Communications
关键词
T梁
预应力张拉
带模蒸气养生
安全
T - girder
Prestressed stretch - draw
Model - stream curing
Safety