摘要
对南京地铁二号线矿山法区间渗漏水进行了分析,从防水设计与施工、渗漏水处理等方面进行了论述,提出了隧道渗漏水点处理的方法,进行了地下工程渗漏水处理的技术研究,达到了治理隧道渗漏的效果,解决了地下工程因防水等施工后仍然渗漏水的问题。
The thesis analyzes the leakage happened in No. 2 line mine mountain interval of Nanjing subway, and the discussion is done from the aspects of waterproof design and construction, leakage treatment and etc. It proposes the treatment method for tunnel leakage points, has a research on underground project leakage treatment technologies, and reaches the effect to treat tunnel leakage, and resolves the repeatedly leakage after underground waterproof project.
出处
《山西建筑》
2010年第28期312-313,共2页
Shanxi Architecture
关键词
隧道
渗漏
治理
tunnel, leakage, treatment