不同温度下悬索桥锚跨索股的张拉力 被引量:7

Strand Tension in Anchor-Span Suspension Bridge at Different Temperatures
下载PDF
导出
摘要 通过简化公式计算和程序计算两种方法研究了温度对边跨索股张拉力、锚跨索股张拉力的影响,并以广州珠江黄埔大桥为例进行算例分析,结果表明:两种方法的计算结果基本接近;散索鞍固定时,温度变化对锚跨张拉力的影响远大于边跨,对边跨索股张拉力的影响系数在-1 kN/℃左右,对锚跨索股张拉力的影响系数达-6~-7 kN/℃;当温度变化超过张拉理想温度范围时,边、锚跨处索股索力差值将大于鞍座提供的最大静摩擦力,具体施工时,须采取一定的防滑措施;散索鞍自由时,温度变化对锚跨索股张拉力影响很小. Two methods,one is based on the simplified expression and the other is on the calculation program,are proposed to reveal the influence of temperature on the strand tensions in the anchor span and each side span of suspension bridge,with Zhujiang Huangpu Bridge in Guangzhou as an example.It is found that the calculated results obtained from the two methods are approximate to each other,that temperature variation has a greater influence on the tension in anchor span than on that in side span when the saddles are fixed,that the influence coefficient of temperature in side span and anchor span are respectively about-1kN/℃ and-6~-7kN/℃,that the force difference between side span and anchor span may go beyond the maximum friction when the temperature change exceeds the ideal range,so that some countermeasures should be taken to avoid the strand sliding during the construction,and that the influence coefficient of temperature in anchor span is very small when the saddles are free.
出处 《华南理工大学学报(自然科学版)》 EI CAS CSCD 北大核心 2010年第9期118-122,共5页 Journal of South China University of Technology(Natural Science Edition)
基金 国家"863"计划项目(2006AA11Z120) 重庆交通大学(桥梁)结构工程重点实验室开放基金资助项目(CQSLBF-Y10-6)
关键词 温度 悬索桥 锚跨 边跨 张拉力 摩擦力 temperature suspension bridge anchor span side-span tension friction
  • 相关文献

参考文献11

二级参考文献26

  • 1陈常松,陈政清,颜东煌.柔索索力主频阶次误差及支承条件误差[J].交通运输工程学报,2004,4(4):17-20. 被引量:16
  • 2张乃华.小贝尔特海峡公路悬索桥的上部结构安装[J].国外桥梁,1993(4):241-252. 被引量:1
  • 3王峻 杨宁 吉林.江阴长江公路大桥主缆施工[A].见:江苏省长江公路大桥建设指挥部.江阴长江公路大桥工程建设论文集[C].北京:人民交通出版社,2000..
  • 4Irvine H M.Cable structures[M].London:The MIT Press,1981.
  • 5O'Brien T W,Francis A J.Cable movements under two-dimensional loading[J].J Struct Eng Div(ASCE),1964,90(ST3):89-123.
  • 6Coyette J P,Guisset P.Cable network analysis by a nonlinear programming technique[J].Eng Struct,1988,10:41-46.
  • 7罗喜恒.悬索分析方法综述.结构工程师,2003,:1-8.
  • 8Peyrot A H,Goulois A M.Analysis of cable structures[J].Computers and Structures,1979,10(5):805-813.
  • 9Jayaraman H B,Knudson W C.A curved element for the analysis of cable structures[J].Computers and Structures,1981,14(3-4):325-333.
  • 10小川英信 多田和夫 杉田卓男.大鸣门桥のケブル架设工事[J].桥梁と基础,1983,(10):30-38.

共引文献69

同被引文献34

引证文献7

二级引证文献24

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部