模块化施工在AP1000建设过程中的应用,给管道安装工作带来很大挑战。本文通过对AP1000管道安装的特点和质量控制要求的介绍,分析了首台AP1000机组在管道安装过程中遇到的难点,为后续模块化施工的规模应用,总结了初步经验,并提出了改进工作的建议。
Modularization construction applies during the AP1000 construction,which is the challenge to the piping system installation. Through introducing the characteristic of piping system installation and requirements of quality control, this paper analyzed the risk during the piping systems Installation in the first AP1000 plant, got construction experiences and gave some suggestions for the wide application of modularization construction in the future.