摘要
通过混凝土搅拌、运输、浇筑温度的分析计算和保温墙模复合剪力墙结构体系冬期施工临界强度分析,得出以下结论:在运输过程满足技术要求的情况下,轻骨料免拆保温墙模复合剪力墙结构体系冬期施工时,不需要对浇筑的混凝土采取保温措施,即可满足冬期施工临界强度的要求。
Through analyzing and calculating concrete mixing, transportation, and pouring temperature, and analyzing the critical intension of the concrete of shearing wall with light aggregate concrete moulding board by way of synthesized accumulate heat as well, it draws following conclusions: under the condition of transportation process meeting technical need, the construction of light weight aggregate concrete moulding boerd structure system in winter, which do not need to take the concrete casting, can satisfy critical intensicn requirement in winter construction
出处
《山西建筑》
2010年第29期128-129,共2页
Shanxi Architecture
关键词
保温墙模
复合剪力墙
结构体系
温度分析
insulation wall module, composite shear wall, structure system, temperature analysis