基于S型ProA生长曲线的产品开发过程时间估算

Time estimation method for product developmen process based on S-shaped growth curve of ProA
下载PDF
导出
摘要 为提高开发过程ProA时间估算的精度和动态性,引入当量的概念,研究了ProA入出项当量及其属性,提出了ProA生长曲线的概念,剖析了原子ProA的生长曲线以及生长曲线的合成关系,由此构建了开发过程的时间估算方法及估算模型,并通过应用分析验证了该方法和模型的可行性。 To raise precision and dynamics of Activity and its Process(ProA)time estimation in product development process,the concept of equivalent was firstly introduced,and equivalent attributes of ProA input and output item were studied. Furthermore,the concept of growth curve was proposed. Growth curve of atomic ProA and synthetic relationship of growth curves were also discussed in detail. Then,time estimation method and estimation model of product development were established. Finally,the feasibility of the method and model was illustrated by application example.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2010年第9期1875-1880,共6页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(70472066 70771091) 国防科技工业技术基础研究资助项目(Z142008A001) 西北工业大学人文社科与管理振兴基金资助项目(RW201002)~~
关键词 产品开发 时间估算 当量 生长曲线 product development time estimation equivalent growth curve
  • 相关文献

参考文献4

二级参考文献35

  • 1徐志勇,张开富,李正兰,姜寿山.一种面向航空产品的分级网络计划方法[J].计算机集成制造系统,2006,12(5):727-730. 被引量:6
  • 2沙全友,王伟,韩毅,郝京辉.面向航空产品项目管理网络计划模型研究[J].计算机工程与应用,2007,43(6):99-101. 被引量:10
  • 3张宏国,徐晓飞,战德臣.基于工作分解结构的跨企业项目多级网络计划[J].计算机集成制造系统,2007,13(3):513-519. 被引量:19
  • 4L. H. Putnam and W. Myers. Industrial Strength Software - Effective Management Using Measurement [ M 1. IEEE Computer. IEEE Computer Society Press, 1997.
  • 5Nan- Hsing Chiua and Sun- Jen Huang. The Adjusted Analogy -Based Software Effort Estimation Based on Similarity Distances [ J]. Journal Of Systems and Software. April 2007, 80(4) : 628 -640.
  • 6张俊光 吕廷杰.软件项目监督与控制方法研究.中国管理科学,2006,(10):127-132.
  • 7Pappas, D. Contingency Reserves: False Expectation and Misconceptions [ C ]. Fifth European Project Management Conference. June 19 -20, 2002. Cannes, France.
  • 8Heimann, J. F. Contingency Planning as a Necessity Proceedings of the Project Management Institute Annual Seminars & Symposium. September 7 - 16, 2000. Houston, Texas, USA.
  • 9Amir Azaron and S. M.T. Fatemi Ghomi. Lower Bound for the Mean Project Completion Time in Dynamic PERT Networks [ J ]. European Journal of Operational Research. 1 April 2008, 186( 1 ) : 120 - 127.
  • 10田俊国.软件项目规模估计方法介绍[EB].http://pm.csai.cn/cost/N0044.htm.