高炉冷却壁热应力试验分析 被引量:3

Experiment Analysis of Thermal Stress in the Cooling Wall of Blast Furnace
下载PDF
导出
摘要 采用脆性涂层法和电阻应变法实际测量了高温状态下高炉冷却壁的应力和应变.实测结果表明:由于冷却水管的非均匀布置,冷却壁中心位置应力较高,而四周应力较低,高炉冷却壁的应力分布,与有限元的应力分布计算结果的趋势和数量级相同.这种测量方法的应用为应力应变的理论计算提供了一种新的校验方法. The measurement result of actual strain and stress of the cooling wall in the blast furnace at high temperature state was obtained by the method of brittle coating and strain gauge line.Its showed that the stress is higher in central position than in the peripheral position because of the nonuniform distribute of water pipe.The tendency and order of calculation result is the same as the measurement.Its application leads to a new measurement method for calibrating the theory calculation result of the stress and strain.
出处 《北京科技大学学报》 EI CAS CSCD 北大核心 1999年第2期125-127,共3页 Journal of University of Science and Technology Beijing
基金 国家"九五"科技重点攻关项目
关键词 冷却壁 脆性涂层 电阻应变 热应力试验 高炉 cooling wall high temperature,stress measurement
  • 相关文献

参考文献10

  • 1杨为国.高炉冷却壁三维温度场的计算(硕士论文)[M].北京:北京科技大学,1997,3..
  • 2刘全武.高炉冷却壁温度场的实验研究(硕士论文)[M].北京:北京科技大学,1998,2..
  • 3张如一 陆耀桢.实验应力分析[M].北京:机械工业出版社,1984.20.
  • 4程素生.高炉长寿高效技术的研究(博士后出站报告)[M].北京:北京科技大学,1998,2..
  • 5程素生,博士后研究工作报告,1998年
  • 6刘全武,硕士学位论文,1998年,2页
  • 7杨为国,硕士学位论文,1997年,3页
  • 8刘鸿文,材料力学,1985年,88页
  • 9郑秀瑗,应力应变电测技术,1985年,18页
  • 10张如一,实验应力分析,1984年,20页

共引文献6

同被引文献22

  • 1宗燕兵,郭发军,赵增武,何鹏,苍大强,佘京鹏,吴启常,佘克事.圆孔型铜冷却壁冷面及热面热态特性研究[J].包头钢铁学院学报,2004,23(3):207-210. 被引量:2
  • 2沈宗斌,任立斌.不同材质高炉冷却壁热应力计算[J].北京科技大学学报,1995,17(6):517-519. 被引量:2
  • 3石琳,程素森,冯力,沈猛.冷却水管表面合金化球墨铸铁冷却壁的热态实验研究[J].炼铁,2006,25(2):26-29. 被引量:10
  • 4Heinrich P.Copper Stave for Blast Furnace Cooling System[J].Asia Steel,1997,47(2):67-74.
  • 5Miller K.Cast Copper Stave An Economic Alternative [A].Ironmaking Conference Proceedings[C].Nashiille:The Iron and Steel Society,2000.191 - 201.
  • 6Helenbrook R G.Water requirements for blast furnace copper staves[J].Iron and Steel Maker,2000,27(6):45 - 51.
  • 7Shinichi S.Cast copper cooling stave for blast furnace [A].Ironmaking Conference Proceedings[C].Nashiille:The Iron and Steel Society,2000.201 - 210.
  • 8Hathaway W R,Nanavati K S,Wakelin D H.Copper slave installation in H-4 blast furnace stack-first result[A].58th Ironmaking Conference Proceedings[C].Nashiille:The Iron and Steel Society,1999.35 - 40.
  • 9Bout L,Delenghe H,Depamelare M.Installing copper staves and operational practice at sidmar[J].Iron and Steel Engineer,1999,76(6):43 - 50.
  • 10吴狄峰 程树森.埋纯铜管铸铜冷却壁传热性能研究[J].冶金研究,2006,60.

引证文献3

二级引证文献28

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部