北京地铁四号线隧道辐射井降水施工实践 被引量:2

Construction Practice of Tunnel Radiation Well Dewatering of Beijing Metro No.4 Line
下载PDF
导出
摘要 在交通复杂、人口密集的城市中心区修建地下隧道,如何降低地下水,是影响施工的关键问题。文中以北京地铁四号线黄庄—中关村区间隧道施工降水为例,从辐射井降水原理着手,介绍了一套占地面积小、降水控制范围大、疏干效果好的施工降水方法。实践证明:竖井采用沉井工艺,水平井采用水力双壁钻杆反循环工艺,可达到快速高效降水的目的,且造价较井点降水节约30%。 Underground water reduction is the key issue for underground tunnel construction in urban central area with complex traffic and dense population.Taking tunnel dewatering construction in Huangzhuang-Zhongguancun Section of Beijing Metro No.4 Line as an example,this paper introduces a dewatering method with small land area,large control range and good draining effect from the principle of radiation well.It is proven from practice that shaft with sinking process and horizontal well with hydraulic double-wall drill pipe reverse circulation process can achieve rapid and effective dewatering and save 30 % compared with well point dewatering.
作者 陈锡云
出处 《路基工程》 2010年第5期159-161,共3页 Subgrade Engineering
关键词 辐射井 降水 沉井 双壁钻杆水力反循环 施工 radiation well dewatering open caisson double-wall drill pipe hydraulic reverse circulation construction
  • 相关文献

参考文献3

二级参考文献6

共引文献30

同被引文献21

引证文献2

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部