电力系统在进行电力供应时,原有的城市架空线路逐步被电缆所替代,城市无杆化已成为城建工作的重要部分,加上城市建设道路拓宽等原因,使用城区内l0kV外网配套施工量越来越大。但是由于电缆埋藏于地下,运行环境复杂,使电缆故障的寻找较为困难,因此,在施工时一定要从型号、敷设、电缆头制作及在施工过程中要考虑问题等进行分析,确保施工质量,提高电力系统供电可靠性、减少用户和供电部门的经济损失。
When power system is conducting power supply,the original city overhead lines are gradually replaced by cable. The pole-free has become an importance of city construction work. Reasons such as road widening of cities make the work load of 10kV facing wire grow. However, since the cable buries under the ground, the operation environment is complex which make the finding of cable fault difficult. Therefore, we should consider problems such as model, laying and fabrication of cable head in the construction process to ensure construction quality and improve power system power supply reliability and reduce the economic loss of customers and power supply departments.
出处
《价值工程》
2010年第30期253-253,共1页
Value Engineering
关键词
10kV电力工程
外网配套施工
技术管理
10kV power project
facing wire mating construction