摘要 实时耦联动力试验(RTDHT)是一种将物理模型试验与数值求解计算实时耦联在一起的新型结构动力试验方法。该文基于振动台构建了振动台型RTDHT试验系统,并对其动力特性进行了研究。利用所构建的RTDHT试验系统,研究了一个双层刚架结构的自振特性及动力反应,其中上层框架为物理子结构,而下层框架为数值子结构,通过两部分之间的实时数据交互得到整体结构的动力响应。将双层刚架的RTDHT试验结果与CDM数值计算结果进行了对比,结果表明二者吻合较好,基于该试验系统的RTDHT试验具有较高的精度。 Real-time dynamic hybrid testing (RTDHT) is a novel testing method coupled of physical substructure testing and numerical substructure calculation. In this paper, a RTDHT testing system based on shaking-table is developed and its dynamic response properties are analyzed. The testing system was applied to a two storey rigid frame to test its vibration properties and seismic responses. A specimen containing only the first storey was made, while the behavior of the second storey will be simulated numerically. The whole structure responses were obtained through alternating of the two parts in real time. Testing results by the developed RTDHT testing system were compared with exact results by CDM numerical calculation. It was found that the two methods yield almost identical results. It can therefore be concluded that the structure responses can be obtained precisely by the developed RTDHT testing system.
出处 《工程力学》 EI CSCD 北大核心 2010年第10期57-64,共8页 Engineering Mechanics
基金 国家自然科学基金项目(50779021 90715041)
关键词 工程结构抗震 实时耦联动力试验 振动台 时滞补偿 双层刚架 earthquake resistance of engineering structure real-time dynamic hybrid testing shaking table delay compensation two storey rigid frame
  • 相关文献

参考文献10

  • 1Bairrao R, Vaz C T. Shaking table testing of civil engineering structures-the LNEC 3D simulator experience [C]. Auckland, New Zealand: Proceedings of 12th World Conference on Earthquake Engineering, 2000: 2129.
  • 2Hakuno M, Shidawara M, Hara T. Dynamic destructive test of a cantilever beam, controlled by an analog-computer [J]. Transactions of Japan Society of Civil Engineering, 1969(171): 1-9.
  • 3Mahin S A, Shing P S B, Thewalt C R, Hanson R D. Pseudo dynamic testing method-current status and future directions [J]. Journal of Structural Engineering, 1989, 115(8): 2113-2128.
  • 4Nakashima M, Kato H, Takaoka E. Development of real-time pseudo dynamic testing [J]. Earthquake Engineering & Structural Dynamics, 1992, 21(1): 79- 92.
  • 5汪强,王进廷,金峰,等.实时耦联动力试验方法评述[c]//第17届全国结构工程学术会议论文集.武汉:工程力学杂志社,2008:178-186.
  • 6Horiuchi T, Inoue M, Konno T, Namita Y. Real-time hybrid experimental system with actuator delay compensation and its application to a piping system with energy absorber [J]. Earthquake Engineering & Structural Dynamics, 1999, 28(10): 1121 - 1141.
  • 7Wu Bin, Bao Haie, Ou Jinping, Tian Shizhu. Stability and accuracy analysis of the central difference method for real-time substructure testing [J]. Earthquake Engineering and Structural Dynamics, 2005(34): 705- 718.
  • 8汪强,王进廷,金峰.实时耦联动力试验中作动器反应迟滞对于试验结果的影响研究[C]//首届全国水工抗震防灾学术会议论文集.南京,2006:326-332.
  • 9Wallace M I, Wagg D J, Neild S A. An adaptive polynomial based forward prediction algorithm for multi-actuator real-time dynamic substructuring [C]. Proceedings of the Royal Society, 2005(461): 3807-3826.
  • 10Neild S A, Stoten D P, Drury D P, Wagg D J. Control issues relating to real-time substructuring experiments using a shaking table [J]. Earthquake Engineering & Structural Dynamics, 2005, 34(9): 1171 - 1192.