摘要
随着综放采煤工艺向中小型煤矿普及,越来越多的煤矿采用综放采煤工艺来改造原来落后的普采工艺,使运输顺槽皮带机的安装成了主要问题。详细介绍了长距离大起伏综放运输顺槽皮带机安装工程中需注意的细节及方法。
Along with the popularization of fully-mechanized coal caving technology in small and medium-sized coalmines,more and more coalmines adopt fully-mechanized coal caving technology to transform the original backward conventional mining technology,which makes the installation of gateroad belt conveyor become an important problem.This paper introduces the details of and methods for the installation of fully-mechanized gateroad belt conveyor with longdistance and big-fluctuation.
出处
《科技情报开发与经济》
2010年第27期215-217,共3页
Sci-Tech Information Development & Economy
关键词
煤矿生产
运输顺槽皮带机
安装工程
production of coalmine
gateroad belt conveyor
installation work