摘要
为了模拟110kV线路在出现故障状态下的电源自投保护装置的应用情况,研究制作了模拟开关动作电源板,并在模拟实验中进行了应用。结果表明,该模拟开关电源能够缩短实验时间近3倍,可以有效保障施工及实验安全,使装置平稳运行。
To simulate the application situation of automatic backup power switching unit when 110 kV line is in fault state, one simulation on-off action power panel was made after investigation, and used in the simulation experiment.The result shows, the analog switch power can shorten the experiment time by nearly 3 times, effectively ensure construction and experiment safety, and make the plant running smoothly.
出处
《炼油与化工》
2010年第5期19-21,共3页
Refining And Chemical Industry
关键词
110kV
备自投装置
模拟试验
电力系统
110 kV
auto backup power switching unit
simulation experiment
power system