摘要
通过直接导入三维精确采切设计及开拓设计成果,以生产者及其工效、矿山主要采掘工艺技术为约束,以线性规划为优化技术对矿山采掘计划进行编制,实现了计划编制的三维可视化及动态管理.文章从三维可视化地下矿采掘进度计划编制的基本原理、技术方法和实现手段,全面阐述了三维可视化地下矿采掘进度计划编制系统,并以实际工程应用情况说明了系统的可行性和科学性.
Through introducing and developing three-dimensional exact mining and cutting design, with constraint of producers and their efficiency, mining techniques, and linear programming as optimal design to plan the mining, the three-dimensional visualization and dynamic management of the plan management is achieved. From the aspects of basic principles, techniques and actualizing method of the three-dimensional visualized underground mining plan establishment, this paper sets forth a comprehensive explanation of the plan management system of three-dimensional visualized underground mining, and of its feasibility and scientificity with practical examples in engineering.
出处
《江西有色金属》
2010年第3期88-91,共4页
Jiangxi Nonferrous Metals
关键词
三维
地下矿
采掘进度
计划编制
动态管理
three-dimensional
underground mine
mining schedule
plan management
dynamic management