摘要
随着电网自动化技术的迅速发展,集控中心的数量在迅速增加,集控中心不能遥控站端设备将会影响到电网的安全稳定运行。结合220kV水城集控中心不能遥控所辖110kV某变电站断路器的缺陷为例,初探一下此类问题的处理方法。
Along with the development of power grid automation technology, the amount of centralize control center quickly increase. If centralize control center can not remote control the equipments of transformer substation, that will affect the safety of power grid. We take the case of Shuicheng centralize control center fail to remote control the circuit breaker of transformer substation, we discuss the method to deal with the problem.
出处
《贵州电力技术》
2010年第10期31-32,共2页
Guizhou Electric Power Technology
关键词
集控
遥控
通信
远动
centralize control
remote control
communication
remote act