摘要
要了解特大型水电工程的安全性状,需要通过创新性的监测技术才能实现。以三峡水利枢纽、溪洛渡水电站、向家坝水电站、糯扎渡水电站等特大型水电工程为例,阐述了特大型水电工程安全监测所面临的难题。重点介绍了已完工的三峡工程安全监测工程中的技术创新。说明了特大型水电工程是推动监测技术向前发展的重要平台。
In order to grasp the safety state of extra-large project,innovative monitoring technology should be adopted.Taking TGP,Xiluodu Hydro-project,Nuozadu Hydro-project etc.as examples,we briefly introduce the facing difficulties in safety monitoring of extra-large hydro-projects and give priority to the technology innovation in safety monitoring of the built TGP.The safety monitoring in TGP construction showed construction of extra-large hydo-project can promote development of monitoring technology.
出处
《人民长江》
北大核心
2010年第20期1-4,共4页
Yangtze River
关键词
特大型水电工程
监测技术
技术创新
三峡水利枢纽
extra-large hydro-project
monitoring technology
technology innovation
TGP
Middle Route Project of South to North Water Diversion