摘要
以兴义发电厂两座8500m2双曲线冷却塔同步施工为例,对大型冷却塔施工中的有关问题进行了探讨在该工程施工中,通过合理利用现有的施工机具,对冷却塔垂直运输机具组合配置方案进行优化,以及改进人字柱和通风筒等项目的施工工艺等,确保了工程施工质量和工期。
By the example of constructing synchronized for two 8500m2 hyperbola cooling towers in Xingyi, discussed the problems during large cooling tower construction. The vertical transport machine combination configure project of cooling tower was optioned by using current construction machine reasonably during construction. The construction technique of herringbone column, ventilate canister and so on was improved by using new technology. The construction quality and schedule was guaranteed, and expected target of the cost control was arrived.
出处
《工程质量》
2010年第11期27-29,36,共4页
Construction Quality
关键词
冷却塔
垂直运输机具组合
剥筋滚压直螺纹
粉煤灰
支撑体系
cooling tower
vertical transport machine combination configure
rolling depressed bar with straight thread
flyash
support system