氧化铝项目试车问题探讨

下载PDF
导出
摘要 本文结合中铝遵义氧化铝项目的试车过程,分析了氧化铝项目试车工作的重要性以及项目从单体试车到负荷联动试车的组织、策划、实施要点,阐述了单体试车、无负荷联动试车、负荷联动试车各阶段的特点、目标、任务和工作方法,为氧化铝项目试车的组织和实施提供实践经验。 This article is based on the commissioning of Zunyi Alumina Refinery, analyzing the importance of refinery commissioning and the organization, planning and execution key points from individual unit commissioning to linkage commissioning with load, and stating the characteristics, purpose, duty and method of each stage for individual unit commissioning, linkage commissioning without load and linkage commissioning with load, so as to provide practice experience for organization and execution for alumina refinery commissioning.
作者 王陈胜 袁赤
出处 《工程建设项目管理与总承包》 2010年第6期20-22,共3页 Project Management and EPC/Turnkey Contract
关键词 氧化铝 单体试车 无负荷联动试车 负荷联动试车 试车方案 技术服务 alumina individual unit commissioning linkage commissioning without load linkage commissioning with load commissioning program technical service
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部