摘要 结合禹门口一级泵站所在地水文地质条件,对两种站址方案进行了比较分析,经过计算,指出两方案位置相邻,地质条件相同,基坑涌水量相近,但方案一施工条件优于方案二,从而确定方案一为推荐站址方案。 Combining with the hydrological and geological conditions of the location of the first pumping station at Yumenkou, the paper com- pares and analyzes the two address schemes, and points out the two schemes have the close to each other, with similar geological conditions and water inflow in foundation pits, but the constructing condition of the first scheme excels the second one after calculation, so the first scheme is identified as the recommended pumping station address.
作者 王学勤
出处 《山西建筑》 2010年第35期101-103,共3页 Shanxi Architecture
关键词 泵站 站址方案 地质条件 涌水量 pumping station, station address scheme, geological condition, water inflow