锚桩反力梁慢速维持荷载法桩基静载试验研究 被引量:5

On Pile Foundation Static Loading Test with Anchor Pile Reaction Beam Slow Maintenance Loading Method
下载PDF
导出
摘要 桩基静载试验采用接近于通过竖向抗压桩的实际工作的试验方法,比较准确地反映单桩的受力状况和变形特征,确定单桩竖向抗压承载力,对工程桩的承载力进行抽样检验和评价。结合京沪高速铁路基桩静载荷试验,详细阐述了锚桩反力梁慢速维持荷载法桩基静载试验工艺。 Static load test of pile foundation is closer to the test method of vertical compressive piles in actual work.It reflects the force and deformation characteristics of single pile with a relative accuracy,makes out vertical compressive bearing capacity of single piles,tests and evaluates the bearing capacity of engineering piles by sampling.Combined with foundation pile static loading test in Beijing-Shanghai High-speed Railway,this paper expounds in detail the technique of pile foundation static loading test with anchor pile reaction beam slow maintenance loading method.
作者 王梅
出处 《铁道建筑技术》 2010年第11期42-44,共3页 Railway Construction Technology
关键词 反力梁 静载试验 慢速维持荷载法 reaction beam static load test slow maintenance loading method
  • 相关文献

同被引文献37

引证文献5

二级引证文献20

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部