斯里兰卡汉班托塔港一期工程围堰混凝土防渗墙施工技术 被引量:2

Construction Technique of Concrete Cutoff Wall for the Weir of First-stage Hambantota Port in Sri Lanka
下载PDF
导出
摘要 斯里兰卡汉班托塔港一期工程围堰总长4212m,整个围堰垂直防渗采用塑性混凝土防渗墙的止水型式。在北围堰段淤泥层较厚区域采用下设钢筋网片的刚性混凝土结构,防渗面积约5万m2。施工中成功地解决了临海较厚纯砂层和淤泥层的成槽稳定问题。本文主要介绍防渗墙的施工方法和具有创造性的技术特点。 The total length of the weir of first-stage Hambantota Port is 4212m,the vertical cutoff of the weir adopts plastic concrete cutoff wall.Reinforced concrete cutoff wall is used in the northern weir where there is a relatively thick layer of silt,the total area of the cutoff wall is about 50000 m2.During the construction of the cutoff wall,the difficulty of stabilizing the walls of the trench was successfully solved in the relatively thick sand layer and the silty layer adjacent to the sea.This article dedicates to introduce the construction method of cutoff wall and the creative technique features of the project.
出处 《机电产品开发与创新》 2010年第6期188-190,共3页 Development & Innovation of Machinery & Electrical Products
关键词 汉班托塔港 防渗墙 塑性混凝土 钢筋网片 海相淤泥 特殊地层 hambantota port cutoff wall plastic concrete reinforcement fabric marine silt special strata
  • 相关文献

同被引文献3

  • 1中国水电基础局有限公司.预制混凝土导墙[R].北京:中华人民共和国知识产权局.专利号ZL200920107631.8.2010.
  • 2中国水利水电基础工程局DT/T5199-2004水利水电工程混凝土防渗墙施工技术规范[S].北京:中国电力出版社,2004.
  • 3中华人名共和国水利部.SL345-2007水利水电工程注水试验规程.北京:中国水利水电出版社,2008.

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部