摘要
根据西江23-1油田的开发实例,重点对西江23-1油田FPSO(海洋石油115)与内转塔单点系泊系统的海上安装回接进行论述,并且给出了精确的回接数据和后续施工的建议,以此对未来这一领域的发展提供海上安装工艺方面的经验和说明。
Single Point Mooring (SPM) system and FPSO have been the main model for developing offshore oil and gas project for recent years in the South China sea.' SPM system needs to be installed on offshore site before FPSO reaches the field. After installation, FPSO hooks up the SPM before oil/gas field first production. The installation procedure and hook-up details according to the Xijiang 23-1 project experience is presented in this article. Xijian 23-1 project's FPSO is HYSY115 and the SPM system is Submerged Turret Production(STP). Furthermore, the actual data and advice are mentioned. And this article would provide a good guideline and instruction for the future installation and hook-up of STP project.
出处
《中国造船》
EI
CSCD
北大核心
2010年第A02期386-391,共6页
Shipbuilding of China
关键词
单点系泊
回接
安装工艺
SPM
hook-up
offshore Installation