河南平顶山市中兴路活动中心工程由于施工违规造成边坡出现裂缝、渗水、失稳,发现情况后采取坑外卸载、跟踪注浆法、排水、喷混凝土面层、增设锚杆等处理措施,使基坑处于稳定状态。
In an activity center project located on Zhongxing Road of Pingdingshan City, Henan Province, some problems, such as crack, water seepage and destabilization, are found on side slope due to construction violation, and some measures, such as out-pit unloading, tracing compensation grouting, water drainage, concrete surface and anchor rod, are adopted to keep the foundation pit stable.