摘要
文章阐述了缅甸瑞丽江一级水电站至达贡山镍矿220 kV送电线路工程拼抢工期的若干措施,尤其指出大件材料在雨季前运输到现场材料站、将组织不力的施工分包商断然换下、对雨季材料中运的路面进行处理等措施的施行,能使工程满足合同对工期的要求。实践表明,这些非常措施对赢得工程工期是行之有效的。
The article illustrates several measures to Strive for Punctuality in the 220 kV Transmission Line Project from Myanmar Shweli First-class Hydropower Station to Dagon Hill Nickel Mine,and points out especially that bulky materials should be sent to material station before rainy season,construction subcontractors who could organize well should be dismissed and measures to cope with road surface in rainy seasons.Therefore the project can meet the time requirement in the contract. In practice,it has shown that these unusual measures are effective to win time.
出处
《企业科技与发展》
2011年第1期52-54,共3页
Sci-Tech & Development of Enterprise
关键词
缅甸
输电线路
拼抢工期
措施
Myanmar
transmission line
strive for punctuality of project
measures