介绍了周口隆达发电有限公司2×135MW机组脱硫技术改造工程和机组烟囱概况,分析了烟囱运行工况和影响因素,提出了烟囱防腐改造前的运行调整措施及烟囱防腐改造方案。
The desulphurization technical reformation project of the 2×135 MW unit of Zhoukou Longda Power Generation Corporation Limited and the unit chimney were introduced.The chimney operation conditions and the influencing factors were analyzed.The anti-corrosion reformation scheme of the chimney was put forward,and the operation regulating measures for the chimney before anti-corrosion reformation were given too.
出处
《华电技术》
CAS
2010年第12期78-80,共3页
HUADIAN TECHNOLOGY
关键词
脱硫技术改造
烟囱防腐
影响因素
改造方案
desulphurization technical reformation
chimney anti-corrosion
influencing factor
reformation scheme