摘要
介绍新疆北部某水电站的工程概况,通过对坝址及流域洪水、泥沙、径流和冰情等水文,气象条件的分析,提出了混凝土面板堆石坝施工导流。
An introduction was made on the general of a hydropower station located in the Northern area of Xinjiang.Based on analysis of the hydrological and meteorological conditions of the dam site and river basin including flood,sediment,runoff and ice regime etc.,the Construction diversion and river closure design scheme of concrete slab rockfill dam was put forward.
出处
《广西水利水电》
2010年第6期38-40,共3页
Guangxi Water Resources & Hydropower Engineering
关键词
施工导流
截流
导流洞
设计
Construction diversion
river closure
diversion tunnel
design