电容器由于结构、接线方式的不同,其内部故障保护的配置和整定存在较大的差别。文章从某变电站35 kV电容器群爆入手,根据发生后的现场记录、故障后的电气试验结果、电容器现场安装情况,并利用PSCAD对故障过程进行了仿真分析和故障重现,通过对事故原因的分析和讨论,吸取了此次事故的教训,提出了一些改进建议,希望能够为今后运行提供参考。
The capacitor, due to different structure and wiring mode, has big difference in its disposition and setting of the internal protection. Starting with external fuse group explosion of 35 kV capacitor at certain substation; based on PSCAD, the fault process is simulated and analyzed and fault reproduction is made according to site record, electrical test result and installation of capacitor after the fault. The lesson on the fault is summarized through analysis and discussion of the fault, and some improvement suggestions are proposed so to provide reference for the future operation.
出处
《电力电容器与无功补偿》
2010年第6期43-46,60,共5页
Power Capacitor & Reactive Power Compensation
关键词
电容器组
熔丝群爆
故障分析
capacitor bank
fuse group explosion