在珊瑚礁地质条件下,先冲孔穿透珊瑚礁再钻孔施工灌注桩,在国外设备受限的条件下完成了任务,对于工程量不大的项目起到了很好的效果,在类似工程中可以借鉴。
Under the geological condition of coral reef,punching the coral for the first and then drilling piles are accomplished while it is restricted on foreign equipments,it makes good effects for the projects with less work amount,can provide references for similar engineering.
出处
《中国港湾建设》
北大核心
2010年第6期58-60,共3页
China Harbour Engineering
关键词
钻孔灌注桩
珊瑚礁
成孔
施工工艺
bored pile
coral reef
drilling hole
construction technology