摘要
介绍某液压综合试验台液压泵站的设计过程,给出液压管路的计算方法,使用CATIA V5建立液压泵站装配图,避免了设计过程中的一些错误,得到了满意的实际运行效果。
The design process of the hydraulic pump station of the hydraulic test bed was introduced. The method of pipeline calculation was carried out. The assembly drawing of hydraulic pump station was built by using CATIA VS. Some mistakes can be avoided and a satisfying effect is achieved.
出处
《机床与液压》
北大核心
2010年第24期57-58,66,共3页
Machine Tool & Hydraulics