介绍河北马头发电有限责任公司200MW机组循环流化床烟气脱硫(CFB-FGD)系统的组成及工作流程,分析其投产后吸收塔床层压降不稳定造成塌床的原因,并提出了有针对性的解决措施。
This paper introduces the composing and work flow of Hebei Matou Power Generation Co.Ltd.200MW unit circulating fluidized bed desulfurization (CFB)FGD,analyzes the causes of collapsed bed by absorption tower pressure drop after the operation,and put forwards effective settlement measures.
出处
《河北电力技术》
2010年第6期37-38,共2页
Hebei Electric Power