摘要
介绍了百米级大落差胶凝材料气力输送的方法,论述了大落差胶凝材料气力输送技术方案的合理性和可行性,为小湾水电站建安期大落差胶凝材料的输送提供了现场试验数据及技术方案。
The method of pneumatic conveying of cementitious material with hectometer-level large drop was introduced.The rationality and the feasibility of the technical scheme of pneumatic conveying of cementitious material with large drop were expounded,which provides the site experimental data and the technical scheme for Xiao-wan Hydropower Station to convey the cementitious material with large drop in its construction and installation period.
出处
《华电技术》
CAS
2011年第1期63-64,81,共2页
HUADIAN TECHNOLOGY
关键词
大落差
胶凝材料
气力输送
试验
large drop
cementitious material
pneumatic conveying
test