摘要
介绍了海上风电机组安装组拼时下塔筒的安装工艺,分析了水平运输和竖直运输两种安装工艺的特点,得出了竖直运输工艺具有更高的安全性、经济性及施工效率的结论,最后对竖直运输工艺的可行性、技术要求与安装要点进行了详细描述。
This paper is concerned with the installation technology of offshore wind turbine bottom tower.Two kinds of installation technology,horizontal transport and vertical transport,are analyzed,and vertical transport technology is selected,because of vertical transport has higher level of security,economy and construction efficiency.Then,the feasibility,technical requirements and installation elements of vertical transport technology are described in detail.
出处
《装备制造技术》
2011年第1期140-143,共4页
Equipment Manufacturing Technology
关键词
海上风电机组
下塔筒
竖直运输
安装工艺
offshore wind turbine
bottom tower
vertical transporty
installation technology