大断面隧道掘进机实施洞内组装和“绿色组装”理念 被引量:1

Experience of On-site Assembly and "Green Assembly" of Large TBM in Tunnel Chamber
下载PDF
导出
摘要 四川雅砻江锦屏二级水电站C4标段1#隧洞采用401-319 TBM施工,此TBM整体结构分为主机、连接桥、后配套及其辅助系统,是目前亚州直径最大的敞开式硬岩掘进机。文章主要介绍在有限空间内实施大断面掘进机洞内组装的技术措施和工艺流程,其中主要包括:"绿色组装"理念、组装前的准备工作、组装洞室的设计原则、工艺流程及重点部位安装方法、环境保护等。 Taking TBM 401-319 for No.1 diversion tunnel on Lot C4 of Jingping II Hydropower Plant for example,this article focuses on the experience of on-site assembly and green assembly of large TBM in a tunnel chamber.Technical measures and process are introduced,including concept of green assembly,preparatory work before assembly,design principles of assembly chamber,assembly of important parts and environment protection.
出处 《现代隧道技术》 EI 北大核心 2010年第6期46-50,共5页 Modern Tunnelling Technology
关键词 大断面掘进机 组装洞室 绿色组装 Large cross-section TBM Assembly in chamber Green assembly
  • 相关文献

参考文献5

二级参考文献1

  • 1Willames J H,Davies A,Drake P R.Condition-Based ma-intenance and machine diagnostics[]..1994

共引文献22

同被引文献7

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部