摘要
以漳山电厂一期2×300MW工程为例,分析了WG2-1045/17.5-7型四角切圆锅炉运行过程中存在的不足,详细介绍了如何对WG2-1045/17.5-7型锅炉燃烧技术进行优化。
Taking the first phase of 2×300 MW project of Zhangshan Power Plant as an example,this paper analyzes some shortages existing in the operation of WG2-1045/17.5-7 corner tangential boiler,and introduces in detail how to optimize the combustion technology of WG2-1045/17.5-7 boiler.
出处
《科技情报开发与经济》
2010年第36期167-169,共3页
Sci-Tech Information Development & Economy