摘要
结合相关试验单位资料对清江水布垭电站发电机组首次启动并网的整体系统试验进行了总结,重点阐述了机组充水后启动试验和机组并网及并网后特殊试验。电站总体试验情况良好,基本上满足了建设方、管理方及电网方面保证电站安全交接和日后安全运行的要求。可为现代大、中型水轮发电机组首次启动并网系统试验提供借鉴作用,有一定的实用参考价值。
In combination with the relevant tests data,the overall system test is summarized on the first launch of synchronization test of Qingjiang shuibuya hydropower station generator units,emphatic on water-filled unit launch test and unit synchronization and special test after synchronization.The overall test is in good condition,basically meeting the needs of the construction side,the management side and the power grid to ensure the safety transfer of the station and future safe operation.For the modern large or medium-sized hydro-generating unit of initial synchronization test,this paper has certain practical reference value.
出处
《华中电力》
2010年第4期61-65,共5页
Central China Electric Power
关键词
水轮发电机组
首次启动并网试验
总结
hydro-generating unit
first launch of synchronizationtest
summary