摘要
用电弧炉和AOD双联冶炼核电站主管道Z3CN2009M,并根据Shaefler图计算结果调整Z3CN2009M的铁素体含量。在离心铸管工艺中,用加大型筒壁厚、减小档板内孔直径、选大的重力加速度g值、增加内孔加工余量等措施铸造出主管道样件。测试结果表明,主管道样件各项性能指标均满足RCCM的要求。
Primary piping steel of Z3CN20 09M for nuclear power plant is melted by combination of electric furnace and AOD furnace,ferrite content of Z3CN20 09M are adjusted based on the compute result of Scharffler.Measures by enlarging the wall thickness of shell,decreasing inside diameter of the baffle,selecting greater g value and increasing machining allowances of internal surface,etc,in centrifugal casting process,sample of primary piping are casted.Measure results show that various performance of sample of primary piping the needs of RCC M are without exception meet.
出处
《核动力工程》
EI
CAS
CSCD
北大核心
1999年第4期357-359,共3页
Nuclear Power Engineering
关键词
压水堆
核电站
主管道
铸造
不锈钢管
PWR Nuclear power plant Primary piping Casting Duplex smelt