摘要
为便于施工资源宏观管理,制定宏观的集结生产计划,利用最优化理论建立数学模型,优化施工物料集结生产计划,使总费用最低;考虑生产均衡性,以生产计划均衡性为上层目标,建立双层目标的规划模型,满足施工物料生产强度或供应强度的均衡性要求。最后以大岗山水电站厂房人工骨料系统为例,对集结生产计划进行优化,使施工资源均衡化。
In order to facilitate the macro-management of construction resources and draw up aggregation plan,we establish a mathematical model by optimization theory to optimize the aggregation plan of construction materials,so the total cost will be the lowest.Considering the balance of production,we also establish a bi-level planning model taking the production plan balance as the upper level goal to meet the balance requirements of production intensity or supply intensity of construction materials.Taking the artificial aggregate system of Dagangshan Powerhouse as an example,the aggregation plan is optimized to balance the construction resources.
出处
《人民长江》
北大核心
2011年第3期72-75,82,共5页
Yangtze River
基金
四川省学术带头人培养基金资助项目(2200118)
关键词
施工物料
生产计划
最优化
双层规划
均衡性
资源平衡
construction materials
production plan
optimization
bi-level planning
balance
resource balance