摘要
运用多Agent模拟和离散模拟方法对参与者的行为变化和工程的完成过程建模,对他们之间的相互作用关系进行模拟,通过几个示例对比分析在一般的管理模式和集成化管理模式下工程的进度和成本的变化情况,以此来分析和验证集成化管理模式的优越性.
This paper mainly investigated highway construction,studied participants,projects and the interaction between them.In particular,the integrated management mode was analyzed.Participants' behavior and the process of projects were modeled using multi-Agent and discrete simulation respectively.Then,the human-project interaction was simulated.Finally,several tests were performed based on common management mode and integrated management mode in order to validate the advantage of integrated management.
出处
《武汉理工大学学报(交通科学与工程版)》
2011年第1期176-180,共5页
Journal of Wuhan University of Technology(Transportation Science & Engineering)
基金
国家自然科学基金项目(批准号:70671048)