摘要 随着输电线路的发展建设以及输电线路所处地质、地形条件越来越复杂,难免遇到山体垮塌、地震等自然灾害或人为破坏造成铁塔受损,需要更换铁塔主材。四川电力送变电建设公司依托500 kV九石线抢险工程,成功设计应用了铁塔主材更换装置。该装置具有额定承载能力大、结构简单、单件重量轻、方便运输和使用、数字化系统受力监控、安全可靠等特点。 As the development of transmission line construction as well as more and more complexity of the geological and geographical conditions near the lines,the steel tower becomes slant or inclined,which is inevitably caused by human destruction or natural disasters such as mountain sliding and earthquake etc.,so it needs to be straightened.Sichuan Electrical Power Transmission Transformation Construction Company has successfully designed a hydraulic straightening system for straightening the steel towers according to the emergency construction project of 500 kV Jiushi transmission line.This system has a large rated load-carrying capacity and simple structure,its single component is light and is convenient for transportation and usage,and it can monitor the stresses of digital system with safety and reliability.
出处 《四川电力技术》 2011年第1期80-82,共3页 Sichuan Electric Power Technology
关键词 抢险 铁塔主材 更换装置 设计 emergency relief principal materials of steel tower replacement device design
  • 相关文献

参考文献4

  • 1架空送电线路铁塔组立工程手册[Z].北京:中国电力出版社,2007.
  • 2高压架空输电线路施工技术手册--起重运输部分[Z].北京:水利电力出版社,1975.
  • 3.GB50017-2003钢结构设计规范[S].北京:中国计划出版社,2003..
  • 4DL/T 875-2004,输电线路施工机具设计、实验基本要求[S].