预压托换桩在深基坑临近建筑物加固及边坡支护的应用研究 被引量:4

Application study on preloading piles technology in reinforcement of buildings next to deep foundation pit and side slop support & protection
下载PDF
导出
摘要 煤矿输煤暗道基坑开挖时造成临近主井驱动机房倾斜和基坑边坡垮塌。采用钢筋混凝土预压托换桩对原主井驱动机房基础加固,通过托换桩将机房荷载传递到承载力较好的持力层,既保证了既有建筑物的安全,又保证了边坡的稳定,加固效果可靠,取得了良好的经济与社会效益,为既有建筑近旁开挖深基坑的边坡支护方法的研究与工程应用方面取得了成功的尝试。 When a coal mine dug foundation pit for blind pass of coal transportation,the nearby main machine room inclined and the side slope of foundation may collapse as a result of digging.In this paper way was figured out to solve this problem.Steel concrete pretest pile was applied to reinforce the primary main machine room,then the load was transmitted to bearing layer which had a better carrying capacity.As a result,the safety of buildings and stability of side slop were ensured;what's more,the achievement of reinforcement was reliable.This technology could bring in favorable profits to both economy and society fields.Also,the preloading piles technology offers a successful new experience for study and engineering application of side slop support protection around deep foundation pit.
出处 《中国安全生产科学技术》 CAS 北大核心 2011年第1期58-62,共5页 Journal of Safety Science and Technology
关键词 预压托换桩 深基坑开挖 基础加固 边坡支护 preloading piles technology deep foundation pit reinforcement of foundation side slop support and protection
  • 相关文献

参考文献11

二级参考文献11

共引文献448

同被引文献32

引证文献4

二级引证文献21

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部