摘要
结合新建青岛客站主站房地下候车室工程实例,依据地下水勘察报告、区域水文地质资料和现场情况,对地下水作用进行了综合分析;对比了钻孔灌注桩抗浮方案与岩石锚杆抗浮方案的优缺点,决定采用岩石锚杆抗浮,并顺利实施,取得了良好效果。
Combined with the example of underground waiting room construction of the main building of newlybuilt Qingdao Passenger Station, underground water effect is generally analyzed according to underground water survey report, regional hydrological data and site conditions. The advantages and disadvantages of cast-in-situ pored pile and rock bolt used for anti-floating program are separately analyzed. Through comparison, rock bolt anti-floating program is proven better and implemented successfully, which has achieved good effect.
出处
《路基工程》
2011年第1期144-145,149,共3页
Subgrade Engineering
关键词
地下室
水作用
抗浮方案
岩石抗浮锚杆
underground room
water effect
anti-float program
anti-float rock bolt