电厂供水水源初步可行性论证 被引量:1

The Preliminary Feasibility Studies on Water Source of Power Plant
下载PDF
导出
摘要 根据某电厂建设规模,对县城污水量进行了预测,论证了电厂取水方案,即该电厂主水源采用城市中水,备用水源采用泵站引水,经论证,供水水源能够满足电厂的要求。 According to the construction scale of a power plant,this paper predicts the sewage quantity of the county town,and argues the water intaking scheme of power plant,in which the main water source of the power plant is the reclaimed water of the town,and the alternate water source is the abstracted water from the pump station,and the conclusion is that the water supply sources can fully satisfy the requirements of the power plant.
作者 史福祥
出处 《科技情报开发与经济》 2011年第1期202-204,共3页 Sci-Tech Information Development & Economy
关键词 电厂 供水水源 城市中水 备用水源 污水量预测 power plant water source reclaimed water of town alternate water source prediction of sewage quantity
  • 相关文献

参考文献3

二级参考文献6

  • 1国家电力公司电力建设研究所.大同第二发电厂零排放设计[M].北京:国家电力公司电力建设研究所,1998..
  • 2常明旺 候继文.工业用水管理技术[M].太原:山西科学教育出版社,1998..
  • 3-.火力发电厂节约用水的若干意见[M].北京:国家电力公司,1998..
  • 4山西省电力科学技术协会.山西省电力公司直属发电厂水源、耗水量及其计量情况调研报告[M].太原:山西省电力科学技术协会,1998..
  • 5王翔,王佩璋.山西节水发电的跨世纪技术展望[J].山西电力技术,1998(3):60-64. 被引量:2
  • 6董全庚.山西水资源的管理与水利建设中的投资机遇[J].山西能源与节能,1999(2):10-15. 被引量:1

共引文献1

同被引文献8

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部