适于全断面岩石掘进机的围岩分类方法 被引量:3

Rock classification method for tunnel boring machine
下载PDF
导出
摘要 为了研究影响全断面岩石掘进机(TBM)掘进速率的地质因素,利用三维离散元程序3DEC建立TBM滚刀破岩三维仿真模型,分析不同的地质条件对TBM掘进速率的影响,根据TBM在围岩中的可钻性对南水北调西线工程中的围岩进行分类。分析结果表明:TBM掘进速率与岩石物理力学性质及岩体中的节理条件密切相关,在一定范围内,围岩强度越低,节理分布越密集,TBM掘进速率越高;而围岩强度越高,节理间距越大,使得TBM掘进速率大大降低。 In order to study the geological factors which impact penetrating rate of tunnel boring machine(TBM),this paper uses three-dimensional discrete element model 3DEC to build simulated models on rock fragment by TBM cutter.It analyzes the influence of different geological conditions on TBM penetrating rate and classified the surrounding rock in west route of south-to-north transfer project according to the drill ability of TBM in surrounding rock.The results show that the penetrating rate of TBM is closely related to the mechanical properties of rock and joint conditions in rock mass.In certain extent,TBM penetrating rate will be increased with the decrease of rock strength or closely distributed joints.TBM penetrating rate will be decreased with the increase of rock strength or rarely distributed joint.Another result is that the surrounding rock by TBM penetrating can be divided into three classes based on the drill ability of TBM in surrounding rock,which can guide the TBM penetrating.
出处 《重庆大学学报(自然科学版)》 EI CAS CSCD 北大核心 2011年第2期136-141,共6页 Journal of Chongqing University
基金 国家科技支撑计划资助项目(2006BAB04A06)
关键词 全断面岩石掘进机 围岩强度 节理 掘进速率 离散元 围岩分类 tunnel boring machine(TBM) rock strength joint penetrating rate discrete element model rock classification
  • 相关文献

参考文献5

二级参考文献27

  • 1王石春,陈光宗,何发亮.中国铁路隧道工程地质的发展[J].铁道工程学报,1996,13(2):48-54. 被引量:11
  • 2尤大鑫等 中国地质学会工程地质专业委员会.洞库爆破围岩分类.全国第三次工程地质大会论文选集[M].成都:成都科技大学出版社,1988.545-550.
  • 3张承娟 中国地质学会工程地质专业委员会.水电工程声波围岩分类指标的探讨.全国第三次工程地质大会论文选集[M].成都:成都科技大学出版社,1988.598-605.
  • 4[1]Broms B B. Methods of calculating the ultimate bearing capacity of piles: a summary[J]. Sol-Soils, Frence, 1966, 5(18-19):21-31.
  • 5[2]Bond A J , Jardine R J. Shaft capacity of displacement piles in a high OCR clay[J]. Géotechnique, 1995, 45(1) 3-23.
  • 6[3]António G F. de Sousa coutinho prediction of the horizontal load-displacement curves of pile groups based on the results of single pile tests[J]. Canadian Geotechnical Journal, 2000. 37(5): 951-962.
  • 7[4]Hamouche K K Leroueil,S Roy M Tension tests on wedge- piles in sensitive clays[J]. Canadian Geotechnical Journal, 2000, 37(4): 918-925.
  • 8[5]Cho Y S Bang, Preber. T Transition of soil friction during suction pile installation[J]. Canadian Geotechnicl Journal, 2002, 39(5): 1 118-1 125.
  • 9[6]Cundall P A. Particle Flow Code in 2 Dimensions zcommand and FISH reference summary[M]. Minnesota: Itasca Consulting Group Inc. 1999.
  • 10Pirest S D, Hudson J A. Estimation of discontinuity spacing trace length using scanline[J]. Int. J. Rock Mech. Min. Sci., 1981, 19: 183-191

共引文献254

同被引文献47

引证文献3

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部