期刊文献+

齐岳山隧道+626溶腔综合施工技术研究 被引量:2

On Comprehensive Construction Techniques in +626 Cavern of Qiyueshan Tunnel
下载PDF
导出
摘要 通过介绍齐岳山隧道"+629"溶腔综合治理手段,通过从开挖施工期间准确探测溶腔,前期放水试验,后期补充勘探,平导贯通后"释能降压"施工,到爆破泄水和结构物施工等方面的详细介绍,为类似的岩溶隧道施工积累了一点经验。尤其在进行"释能降压"施工时,避免了类似宜万铁路其他隧道在泄水施工时对隧道内各种设施、设备的影响,真正做到"完全释能"后在进行开挖施工时,泄水未对隧道其他施工造成任何影响。 Through the introduction of comprehensive treatment measures in "+629"cavern of Qiyueshan Tunnel,this paper accumulates some experience for similar Karst tunnel constructions,which includes accurate detection of the cavern during the excavation period,dewatering test at the earlier stage,complementary detection at the later stage,"energy release and pressure reduction" construction after the completion of parallel guiding adit,as well as blasting sluicing and construction of structural works.In particular,during the construction of "energy release and pressure reduction",to avoid the influence on various facilities and equipment in the tunnel which happened in the sluicing construction of other tunnels such as Yiwan Railway,excavation was carried out after a "complete energy release",so that sluicing didn't affect other tunnel construction.
出处 《铁道建筑技术》 2011年第1期33-37,共5页 Railway Construction Technology
关键词 隧道 岩溶 释能降压 综合治理 tunnel Karst release energy and reduce pressure comprehensive treatment
  • 相关文献

参考文献1

  • 1TB10204-2002.铁路隧道施工规范[S].[S].,..

共引文献164

同被引文献29

引证文献2

二级引证文献25

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部