摘要 邻近带电线路组立铁塔施工给输电工程铁塔组立带来很多不便和安全隐患。采用内悬浮外拉线抱杆进行组塔施工时,临近带电线路组塔对其上拉线和吊件控制绳的布置有较大影响。通过计算拉线与临近电力线路的安全距离,细化输电铁塔组立施工计算模型,总结在多个邻近带电线路工程中采取的内悬浮外拉线抱杆组塔施工技术措施,为其他的邻近带电线路组立铁塔提供参考。 It is very inconvenient and unsafe to assemble towers adjacent to power line.When towers are erected by inside suspension pole with outside pulling wires,the adjacent power line will significantly affect the layout of outside pulling wires and the control ropes for lifting.By calculating the safe distance between the outside pulling wires and the adjacent power line,the calculation model for tower assembling construction is further refined.The paper summarizes the technical measures taken in many projects for assembling towers adjacent to power lines by inside suspension pole with outside pulling wires,which can be used as a reference for similar projects.
出处 《电力建设》 2011年第1期117-120,共4页 Electric Power Construction
关键词 邻近带电线路 内悬浮外拉线抱杆 上拉线 吊件控制绳 组塔技术 安全距离 组塔施工模型 技术措施 adjacent power line inside suspension pole with outside pulling wires outside pulling wires control rope for lifting tower erecting technology safe distance tower assembling model technical measures
  • 相关文献

参考文献9

二级参考文献19

  • 1李庆林.特高压输电线路铁塔组立抱杆的方案选择[J].电力建设,2007,28(3):29-33. 被引量:43
  • 2王运祥.高压架空输电线路内拉线抱杆组塔[M].水利电力出版社,1976..
  • 3DL/T5154-2002,架空送电线路杆塔结构设计技术规定[S].中国电力出版社.2002年.
  • 4DL5009.2-2004电力建设安全工作规程第2部分:架空电力线路[S].
  • 5DL/875-2004,《输电线路施工机具设计、试验基本要求[s].中国电力出版社.2004年.
  • 6Q/GDW153-2006,1000kV架空送电线路施工及验收规范[S].国家电网公司.2007年.
  • 7Q/GDW155-2006.1000kV架空送电线路铁塔组立施工工艺导则[S].国家电网公司,2007年.
  • 8吴洪生.起重工工艺学(中级本)[M].科学普及出版社,1985年.
  • 9王国周,翟履谦.钢结构-原理与设计[M].清华大学出版社,1998年.
  • 10徐新济,李恒增.结构力学[M].同济大学出版社,2004年.

共引文献71

同被引文献31

引证文献5

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部