基于TBM工法的隧洞工程进度定量分析——以引红济石隧洞工程TBM段为例

Quantitative Analysis of Advance Rates of TBM Tunneling——TBM Excavation Lot of a Diversion Tunnel
下载PDF
导出
摘要 文章结合QTBM理论,对引红济石隧洞工程前期的开挖进度数据进行了分析统计,结果表明:该工区TBM在Ⅲ类、Ⅳ类围岩中掘进速率较为稳定,而在Ⅴ类围岩中掘进速率较低;同时,获得了适合该工区的岩体品质参数以及TBM净掘进速率、平均使用率等相关参数;并据此对该工程TBM待开挖段的工程进度进行预测,预测表明剩余6 600 m的开挖尚需4.76年。 This paper used QTBM theory to analyze the data in the first stage TBM excavation lot of the water diversion tunnel from Hongyan river to Shitou river.Results indicated that advance rate of TBM was steady in surrounding rocks of classes III,IV and lower in rocks of classes V.At the same time,rock quality parameters,TBM net advance rate,average utilization rate and other related parameters suitable for the lot were obtained.According to those parameters,it has been predicted that the remaining 6600 meters of TBM excavation will still need 4.76 years.
出处 《现代隧道技术》 EI 北大核心 2011年第1期75-77,89,共4页 Modern Tunnelling Technology
关键词 引水隧洞 QTBM理论 掘进速率 净掘进速率 Diversion tunnel QTBM theory Advance rate Net advance rate
  • 相关文献

参考文献2

  • 1陕西省引红济石调水工程地质勘察报告[R].西安:陕西省水利电力勘测设计研究院,2007.
  • 2引红济石调水工程TBM施工段工程物探工作报告[R].中国煤炭地质总局煤炭资源信息中心,2010,18-23.

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部