摘要
渔子溪电站装机4 ×40 M W, 1972 年全部投入运行。20 多年来该电站水轮机素以稳定性差、过流部件损坏严重、大修周期短、工况很差而闻名。1991 年,为了改善电站的运行状况, 电厂与哈尔滨电机厂合作, 采用鲁布革型水轮机向渔子溪型水轮机转化, 经过较长时间的研究与试验, 对3 号水轮机进行了彻底改造, 于1996 年5 月15日并网运行。运行3 年多来, 机组平稳, 年运行小时提高, 增容达10 % , 改造后效果良好。
Transformation of No5 generating unit of Bapanxia Hydro Station and the application of D179atype runner$$$$ Zhao Tianxiang (Bapanxia Hydro Station) Key Words:turbine's runner, transformation to increase capacity, efficient features, cavitation performances, Bapanxia Hydro Station Abstract:D179atype runner of turbine is a model runner with the good performances for the transformation of No5 turbine in Bapanxia Hydro Station, developed by the Orient Motor Factory The practice shows that its efficiency in large discharge area is obvious higher than the original kV4 runner made in Sweden and it has good cavitation performances Its efficiency of the optimum working condition point could increase 22% than that of the original runner Its efficiency at design point is about 92% Thus it is one of runners with good performances for the water head of 20 m The application of D179atype runner in the transformation of the No5 turbine in Bapanxia Hydro Station and its field test results could be used for reference in the transformation and optimization of other turbines
出处
《水力发电》
北大核心
1999年第9期17-19,共3页
Water Power