文章对石虎塘航电枢纽工程施工导流及施工期通航的有关设计内容进行了详细介绍。该设计方案分期分段多,围堰嵌套多,断航时间短,利用二期围堰临时挡水发电,可供类似工程设计参考。
The article presents a detailed introduction to the design of construction diversion and navigation during construction period for Shihutang Navigation-Power Complex.The design proposes a number of stages,sections and cofferdam nests as well as short shipping interruption,and to generate power through temporary water retaining by the 2nd stage cofferdam,which is referential for similar projects.