摘要 盖下坝水电站坝址河谷为狭窄的"V"形河谷,为此在拱坝坝基河谷设置了人工垫座。技施设计阶段根据实际开挖揭露的岩面线和岩石情况,对垫座结构尺寸及开挖形式作了适当调整。采用有限元法和刚体极限平衡法对垫座稳定及应力进行分析,结构调整后垫座的稳定和应力满足规范要求,对坝体应力没有不利影响。 As the narrow V-type valley in the dam site of Gaixiaba Hydropower Station, the artificial socket was designed for the construction of arch dam. In the construction design, the structure, dimension and excavation of socket were adjusted based on the actual rock conditions exposed by excavation. The socket stability and stress are analyzed by finite element method and rigid block limit equilibrium method, and the results show that the stability and stress of adjusted socket meet the requirements of specifications and the socket has no adverse impact on dam stress.
出处 《水力发电》 北大核心 2011年第2期57-60,共4页 Water Power
关键词 拱坝 垫座 抗滑稳定 盖下坝水电站 arch dam socket sliding stability Gaixiaba Hydropower Station
  • 相关文献

同被引文献10

引证文献2

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部