通过牛郎关互通立交桩基础施工实践对溶洞群地区桩基设计和施工中的若干问题进行了讨论,着重阐述了施工勘探及相关参数的确定,并对施工要点作了说明,为以后类似工程设计与施工提供参考与指导。
Through Niulangguan interchange pile foundation construction practice, it discusses several issues on pile foundation design and construction in water-eroded eaves area, mainly expounds construction survey and the determination of relevant parameters, and demonstrates eonstruction points, which has provided guidance for future similar engineering design and eonstruction.
出处
《山西建筑》
2011年第9期177-178,共2页
Shanxi Architecture
关键词
桥梁
桩基础
溶洞群
施工方法
bridge, pile foundation, water-eroded caves, construction methods