基于二层决策系统的工程项目支付进度优化 被引量:1

Project Payment Progress Optimization Based on Bi-level Decision System
下载PDF
导出
摘要 针对工程项目建设时期业主和承包商在支付进度方面可能的利益冲突问题,分析了业主和承包商在项目组织层级上的纵向主从关系,构建了业主和承包商双方净现值最大化的二层决策系统数学模型,并借鉴多目标优化思想设计了基于Pareto和向量评价的微粒群算法,通过编写Matlab程序实现了模型的求解。实例计算结果表明,采用VEPSO-BP算法能获得多种工程施工进度计划方案和相应工程款支付方案,业主和承包商可根据双方利益选取共赢方案以安排项目进度计划。 According to the profit conflict between the client and the contractor in the project payment scheduling,firstly,this paper analyzes the subordination of the client to the contractor in the project organization and establishes the bi-level decision model with the both side's max-NPV as the goal.Secondly,learning from the multi-objective optimization,it designs a vector evaluated particle swarm algorithms based on Pareto to solve the problem, and edits the program with Matlab.Finally,it obtains a lot of project progress and payment solutions through computing and analyzing an instance example,from which the client and the contractor can choose the desirable one to schedule the project network progress.
出处 《水电能源科学》 北大核心 2011年第3期122-125,共4页 Water Resources and Power
关键词 二层决策 现金流 支付进度优化 PARETO解集 微粒群算法 bi-level decision cash flow payment progress optimization Pareto solution set particle swarm optimization
  • 相关文献

参考文献3

二级参考文献17

  • 1何正文,徐渝,朱少英.具有奖励惩罚结构的项目支付进度问题研究:双重角度[J].系统工程理论与实践,2005,25(10):39-45. 被引量:23
  • 2冯允成.活动网络技术[M].北京:北京航空航天大学出版社,1991..
  • 3Tavares L V.A review of the contribution of operational research to project management[J].European Journal of Operational Research,2002,136(1):1-18.
  • 4Herroelen W,Dommelen V,Demeulemeester E.Project network models with discounted cash flows:A guided tour through recent developments[J].European Journal of Operational Research,1997,100(1):97-121.
  • 5Dayanand N,Padman R.On modeling progress payments in project networks[J].Journal of the Operational Research Society,1997,48(9):906-918.
  • 6Dayanand N,Padman R.Project contracts and payments schedules:The client's problem[J].Management Science,2001,47 (12):1654-1667.
  • 7Dayanand N,Padman R.A two stage search heuristic for scheduling payments in projects[J].Annals of Operation Research,2001,102(1):197-220.
  • 8Ulusoy U,Cebelli S.An equitable approach to the payment scheduling problem in project management[J].European Journal ofOperational Research,2000,127(2):262-278.
  • 9Leu S S, Yang C H, Huang J C. Resource leveling in construction by genetic algorithm-ased optimization and its decision support system application[J].Automation in Construction, 2000,10(1 ) : 27- 41.
  • 10Omkar S N, et al. Vector evaluated particle swarm optimization (VEPSO) for multi-objective design optimization of composite structures[J]. Computers and Structures,2008,86:1 -14.

共引文献20

同被引文献17

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部